Week of 6/5/17 (work hours 6am – 3:30pm)

Construction of granite curb and concrete sidewalk on the south bound side of Main Street from 1189 Main St. to 1209 Main Street (Italian Bistro). Temporary closures of driveways / parking areas in this area will be necessary. Contractor will coordinate with stakeholders.

Thursday – The contractor will be installing precast concrete wall sections and headwalls in the large excavation adjacent to the Bidwell Tavern. There will be a large crane on site in the Bidwell Tavern parking area adjacent to Main St. There will be alternating traffic throughout the day – minor traffic delays.