Week of 6/26/17 (work hours 6am – 3:30pm)

Construction of granite & concrete curb on the north bound side of Main Street in the vicinity of the Bidwell Spirit Shoppe. Temporary closures of driveways / parking areas in this area will be necessary. Contractor will coordinate with stakeholders. (Monday thru Wednesday)

Construction of granite curb and concrete sidewalk on the south bound side of Main Street in front of 1209 Main Street (Italian Bistro). Minor impacts to traffic. Temporary closures of driveways / parking areas in this area will be necessary. Contractor will coordinate with stakeholders. (Thursday thru Friday)

The contractor will be installing underground drainage pipe in Main Street in the vicinity of the Bidwell Tavern & Meet Me On Main. Minor traffic delays. (All week)

NO CONSTRUCTION ACTIVITY JULY 1 THRU JULY 4