Week of 4/24/17 (work hours 7am – 3:30pm)

The contractor will be performing drainage work (precast open channel) adjacent to “Meet Me On Main Street” building. Occasional minor impacts on traffic.

Construction of granite curb, concrete sidewalk and underdrain on the north side of Main Street from 1284 Main Street south to the Bidwell Tavern. Occasional minor impacts to traffic. Temporary closures of driveways / parking areas in this area will be necessary. Contractor will coordinate with stakeholders.