Week of 11/21/16 (work hours 7am – 3:30pm)

Monday thru Wednesday

Excavation and placement of subbase material for driveways on the north side of Main Street between the church and the library. Minor traffic delays due to alternating traffic.

General cleanup of the construction site.

Very limited construction activity this week.

NO CONSTRUCTION ACTIVITY THURSDAY & FRIDAY