Week of 11/27/17 (work hours 7:00am – 3:30pm)

Monday thru Friday
• The contractor will be installing the stamped concrete and completing minor punch list work throughout the project area.
• Eversource is scheduled to be on site moving overhead wires to the new poles.
• The contractor will begin preparing the area for the retaining wall at the Pocket Park (in front of Teleflex).
• Expect minimum lanes closures throughout the project area during working hours.