Week of 11/20/17 (work hours 7:00am – 3:30pm)

Monday thru Wednesday
• The contractor will be installing the stamped concrete and completing minor punch list work throughout the project area.
• Eversource is scheduled to be onsite moving overhead wires to the new poles.
• NO WORK THURSDAY AND FRIDAY. HAPPY THANKSGIVING!
• Expect minimum lanes closures throughout the project area during working hours.