Week of 10/16/17 (work hours 6:30am – 3:30pm)

Monday thru Friday

  • Placing topsoil throughout the project area.
  • Installing decorative light poles and pulling cable on the SB side of Main Street
  • Placing concrete for the remainder of the sidewalk
  • Reconstructing the parking lot between “Meet Me On Main” and the Teleflex Building
  • Minimal lane closures this week