Week of 10/09/17 (work hours 7:00am – 3:30pm)

Monday thru Friday

The contractor will continue with installing concrete sidewalks through the rock cut area and near 1265 Main St where the precast channel walls are.

The contractor will be working on installing the cover for the existing culvert at 1265 Main St and installing the remaining electrical/communication conduits in this area.

The contractor will begin installing topsoil in various locations throughout the project area.

Expect alternating traffic throughout the project area during working hours.