Week of 09/18/17 (work hours 6:30am – 4:30pm)

Monday thru Friday

Contractor will install new concrete driveway ramps at #1349 and #1340 Main St.

Contractor will finish installing the last pieces of Granite Curbing throughout the rock cut area.

Contractor will continue with underdrain, electrical conduit, and concrete sidewalks throughout the rock cut area on the southbound lane side.

Manhole structures will be raised to final grade throughout the project area.

THE SOUTHBOUND TRAFFIC LANE WILL BE GRAVEL UNTIL SEPTEMBER 27th.

PAVING SUBCONTRACTOR IS SCHEDULED FOR SEPTEMBER 27th. (WEATHER DEPENDENT)

MONUMENT HILL ROAD WILL CONTINUE TO BE CLOSED AT THE INTERSECTION OF MAIN ST. (RTE 31) NO THRU TRAFFIC

Minor delays to traffic for alternating traffic throughout the work period hours.