Week of 03/05/18

Contractor will be back to finish the Project starting on Monday March 5th
• Finish backfilling the Precast Retaining Wall in front of Teleflex
• Install concrete sidewalks, stairs, and clock tower in the new “Pocket Park” area in front of the Precast Retaining Wall
• Finish the installation of the Precast Retaining Wall after the “Pocket Park” is in place
• Complete Miscellaneous Punch List work throughout the Project Area
• Very minimal impacts to traffic if at all, work to be done off the roadway

Month of March 2018
• Installation of the Timber Beam Rail at 1203 Main St is scheduled
• Metal Handrail/Protective Rail for the Precast Channel is currently being anodized at the shop, will be scheduled to be installed by the end of the month
• More information will be sent out when we have solid installation dates