Schedule

Week of 02/13/17 (work hours 7:00am – 3:30pm)

Monday thru Friday
Excavation and installation of remaining precast concrete culvert sections on the south side of Main Street next to Meet Me on Main. Weather dependent.
No roadway construction activity this week.

Week of 1/23/17

During the months of January and February the contractor will be performing drainage work only adjacent to Meet Me On Main Street.

There will be no work performed on Main Street during this time period therefore there will be NO impacts on traffic. The contractor is expected to resume work on January 25th.

There will be some sporadic work by Eversource (utility work) which may cause very minor impacts to traffic.

 

Week of January 9, 2017

During the month of January the contractor will be performing drainage work only adjacent to Meet Me On Main Street.

There will be no work performed on Main Street this month and therefore there will be NO impacts on traffic.

There will be some sporadic work by Eversource (utility work) which may cause very minor impacts to traffic.

Weeks of 12/12/16 – 1/2/17

There will be no construction activities until after the New Year.

Week of 12/05/16 (work hours 7:00am – 3:30pm)

Monday thru Friday

Excavation and installation of remaining precast concrete culvert sections on the south side of Main Street next to Meet Me on Main.

Very limited roadway construction activity this week.