Schedule

Week of 7/17/17 (work hours 6am – 4:00pm)

THERE WILL BE ROADWAY CONSTRUCTION FOR THE NEXT THREE WEEKS.

On Monday 7/17 the contractor will begin removing the existing asphalt pavement between the church and the Bidwell Tavern. Following asphalt removal the contractor will excavate down to the grade of the new roadway and then the contractor will begin installing gravel material.

Vehicles will be traveling on gravel material for the next two weeks between the church and the Bidwell Tavern. Paving of this area is scheduled for the week of July 31st.

Alternating traffic will be in effect throughout the week. At certain times driveways and parking areas may be inaccessible. The Contractor will coordinate closures with all stakeholders affected.

Week of 7/10/17 (work hours 6am – 3:30pm)

Construction of granite & concrete curb on the north bound side of Main Street in the vicinity of the Bidwell Spirit Shoppe and the Bidwell Tavern. Temporary closures of driveways / parking areas in this area may be necessary. Contractor will coordinate with stakeholders. Alternating traffic will be in effect throughout the week.

Waterline work on Tuesday in the vicinity of Meet Me On Main on the south bound side of Main Street. Minor traffic delays.

Week of 6/26/17 (work hours 6am – 3:30pm)

Construction of granite & concrete curb on the north bound side of Main Street in the vicinity of the Bidwell Spirit Shoppe. Temporary closures of driveways / parking areas in this area will be necessary. Contractor will coordinate with stakeholders. (Monday thru Wednesday)

Construction of granite curb and concrete sidewalk on the south bound side of Main Street in front of 1209 Main Street (Italian Bistro). Minor impacts to traffic. Temporary closures of driveways / parking areas in this area will be necessary. Contractor will coordinate with stakeholders. (Thursday thru Friday)

The contractor will be installing underground drainage pipe in Main Street in the vicinity of the Bidwell Tavern & Meet Me On Main. Minor traffic delays. (All week)

NO CONSTRUCTION ACTIVITY JULY 1 THRU JULY 4

Week of 6/12/17 (work hours 6am – 3:30pm)

Construction of granite curb and concrete sidewalk on the south bound side of Main Street from the Sanborn Property to 1209 Main Street (Italian Bistro). Minor impacts to traffic. Temporary closures of driveways / parking areas in this area will be necessary. Contractor will coordinate with stakeholders.

The contractor will be installing underground drainage pipe in Main Street in the vicinity of the Bidwell Tavern & Meet Me On Main. Minor traffic delays.

Week of 6/5/17 (work hours 6am – 3:30pm)

Construction of granite curb and concrete sidewalk on the south bound side of Main Street from 1189 Main St. to 1209 Main Street (Italian Bistro). Temporary closures of driveways / parking areas in this area will be necessary. Contractor will coordinate with stakeholders.

Thursday – The contractor will be installing precast concrete wall sections and headwalls in the large excavation adjacent to the Bidwell Tavern. There will be a large crane on site in the Bidwell Tavern parking area adjacent to Main St. There will be alternating traffic throughout the day – minor traffic delays.