Schedule

Week of 5/22/17 (work hours 7am – 3:30pm)

The contractor will be installing two 48” diameter concrete pipes across Main St. at the open channel near the “Meet Me On Main” building. Alternating traffic will be in effect – minor traffic delays.

Construction of granite curb and concrete sidewalk on the south bound side of Main Street from the church north to 1209 Main Street (Italian Bistro). Possible minor impacts to traffic. Temporary closures of driveways / parking areas in this area will be necessary. Contractor will coordinate with stakeholders.

Week of 5/15/17 (work hours 7am – 3:30pm)

The contractor will be installing two 48” diameter concrete pipes across Main St. at the open channel near the “Meet Me On Main” building. Alternating traffic will be in effect – very minor traffic delays.

Construction of granite curb, concrete sidewalk and driveway ramps on the north side of Main Street from 1284 Main Street south to the Bidwell Tavern. Possible minor impacts to traffic. Temporary closures of driveways / parking areas in this area will be necessary. Contractor will coordinate with stakeholders.

Week of 4/24/17 (work hours 7am – 3:30pm)

The contractor will be performing drainage work (precast open channel) adjacent to “Meet Me On Main Street” building. Occasional minor impacts on traffic.

Construction of granite curb, concrete sidewalk and underdrain on the north side of Main Street from 1284 Main Street south to the Bidwell Tavern. Occasional minor impacts to traffic. Temporary closures of driveways / parking areas in this area will be necessary. Contractor will coordinate with stakeholders.

Week of 4/17/17 (work hours 7am – 3:30pm)

The contractor will be performing drainage work (precast open channel) adjacent to “Meet Me On Main Street” building. There will be no impacts on traffic.

Construction of granite curb, concrete sidewalk and underdrain on the north side of Main Street from 1284 Main Street south to the Bidwell Tavern. Possible minor impacts to traffic. Temporary closures of driveways / parking areas in this area will be necessary. Contractor will coordinate with stakeholders.

Week of 4/3/17 (work hours 7am – 3:30pm)

The contractor will be performing drainage work (precast open channel) adjacent to “Meet Me On Main Street”.
There will be no work performed on Main Street during this time period therefore there will be NO impacts on traffic.