Category Archives: Schedules

Week of 10/09/17 (work hours 7:00am – 3:30pm)

Monday thru Friday

The contractor will continue with installing concrete sidewalks through the rock cut area and near 1265 Main St where the precast channel walls are.

The contractor will be working on installing the cover for the existing culvert at 1265 Main St and installing the remaining electrical/communication conduits in this area.

The contractor will begin installing topsoil in various locations throughout the project area.

Expect alternating traffic throughout the project area during working hours.

Week of 10/02/17 (work hours 7:00am – 3:30pm)

Monday thru Friday

PAVING THAT WAS NOT COMPLETED LAST WEEK IS SCHEDULED TO RESUME MONDAY OCTOBER 2nd. THE CONTRACTOR WILL BEGIN ON THE MILLED SURFACE AT THE INTERSECTION OF RTE 31 AND RTE 275. THIS WORK IS WEATHER DEPENDENT.

EXPECT HEAVY DELAYS DUE TO ALTERNATING TRAFFIC DUE TO PAVING, PLEASE FIND ALTERNATE ROUTES IF POSSIBLE.

The contractor will continue with concrete sidewalk through the rock cut area.

The contractor will continue with the water and sewer service for the Town Building at Shoddy Mills.

Week of 09/25/17 (work hours 6:30am – 5:30pm)

Monday thru Friday

Contractor will be raising all structures to final grade through the project area.

The precast channel in front #1265 Main St. and The Bidwell Tavern parking lot is scheduled to be stained on Tuesday September 26th.

PAVING IS SCHEDULED TO START ON WEDNESDAY SEPTEMBER 27th. THE CONTRACTOR WILL BEGIN ON THE GRAVEL SECTION OF THE NEW ROADWAY AND CONTINUE TO PAVE THROUGH FRIDAY. THIS WORK IS WEATHER DEPENDENT.

EXPECT HEAVY DELAYS DUE TO ALTERNATING TRAFFIC DUE TO PAVING, PLEASE FIND ALTERNATE ROUTES IF POSSIBLE.

MONUMENT HILL ROAD WILL CONTINUE TO BE CLOSED AT THE INTERSECTION OF MAIN ST. (RTE 31) NO THRU TRAFFIC. THIS ROADWAY IS EXPECTED TO BE OPENED BY FRIDAY SEPTEMBER 29th.

Week of 09/18/17 (work hours 6:30am – 4:30pm)

Monday thru Friday

Contractor will install new concrete driveway ramps at #1349 and #1340 Main St.

Contractor will finish installing the last pieces of Granite Curbing throughout the rock cut area.

Contractor will continue with underdrain, electrical conduit, and concrete sidewalks throughout the rock cut area on the southbound lane side.

Manhole structures will be raised to final grade throughout the project area.

THE SOUTHBOUND TRAFFIC LANE WILL BE GRAVEL UNTIL SEPTEMBER 27th.

PAVING SUBCONTRACTOR IS SCHEDULED FOR SEPTEMBER 27th. (WEATHER DEPENDENT)

MONUMENT HILL ROAD WILL CONTINUE TO BE CLOSED AT THE INTERSECTION OF MAIN ST. (RTE 31) NO THRU TRAFFIC

Minor delays to traffic for alternating traffic throughout the work period hours.

Week of 09/11/17 (work hours 7:00am – 3:30pm)

Monday thru Friday

Continuing the excavation of the rock cut to lower the new southbound lane to the northbound lane grade and installing granite curbing, underdrain, light bases and concrete sidewalks

THE SOUTHBOUND TRAFFIC LANE WILL BE MOVED INTO THE NEW AND FINAL LOCATION THRU THE ROCK CUT BY THE MIDDLE OF THE WEEK AND THE TRAVEL SURFACE WILL BE GRAVEL

MONUMENT HILL ROAD WILL BE CLOSED AT THE INTERSECTION OF MAIN ST. (RTE 31) NO THRU TRAFFIC

Minor delays to traffic for alternating traffic throughout the work period hours

Week of 09/04/17 (work hours 7:00am – 3:30pm)

Monday NO WORK HOLIDAY

Tuesday thru Friday

Continuing the excavation of the rock cut to lower the new southbound lane to the northbound lane grade and finishing the roadway drainage

Preparing the Precast Open Channel at #1265 Main St. for staining

Minor delays to traffic for alternating traffic throughout the work period hours

Week of 08/21/17 (work hours 6:00am – 3:30pm)

Monday thru Friday

Grading of the Parking lot at #1209 Main St. and the installation of concrete handicap accessible ramps.

Removing existing asphalt and grading of Bidwell Tavern, and Bidwell Package Store parking lots.

Paving of #1209 Main St, Bidwell Tavern, and Bidwell Package Store parking lots.

Continuing the excavation of the rock cut to lower the new southbound lane to the northbound lane grade.

Minor delays to traffic for alternating traffic throughout the work period hours.

Week of 08/14/17 (work hours 6:00am – 3:30pm)

Monday thru Friday

Installation of underground utilities near the precast open channel across the street from Bidwell Tavern.

Grading of the Parking lot at #1209 Main St. and the installation of concrete handicap accessible ramps.

Continuing the excavation of the rock cut to lower the new southbound lane to the northbound lane grade.

Minor delays to traffic for alternating traffic throughout the work period hours.

Week of 7/31/17 (work hours 6am – 5:00pm)

ASPHALT PAVING IS SCHEDULED FOR THE WEEK OF JULY 31ST.

Paving will take place between the church and the Bidwell Tavern.

Alternating traffic will be in effect throughout the week. At certain times driveways and parking areas will be INACESSIBLE. Expect delays and use alternate routes if possible.

If you are concerned about getting trapped in a driveway/parking lot you can park your vehicle in the town lot next to the antique store at 1141 Main Street. This lot is outside the construction area and you will have access to your vehicle at all times.

Week of 7/24/17 (work hours 6am – 4:00pm)

THERE WILL BE ROADWAY CONSTRUCTION FOR THE NEXT TWO WEEKS.

On Monday 7/24 the contractor will continue to excavate down to the subgrade of the new roadway and then the contractor will begin placing new gravel material between the church and the Bidwell Tavern.

Vehicles will be traveling on gravel material for the next week between the church and the Bidwell Tavern. Paving of this area is scheduled for the week of July 31st.

Alternating traffic will be in effect throughout the week. At certain times driveways and parking areas may be inaccessible. The Contractor will coordinate closures with all stakeholders affected.