Category Archives: Schedules

Week of 11/20/17 (work hours 7:00am – 3:30pm)

Monday thru Wednesday
• The contractor will be installing the stamped concrete and completing minor punch list work throughout the project area.
• Eversource is scheduled to be onsite moving overhead wires to the new poles.
• NO WORK THURSDAY AND FRIDAY. HAPPY THANKSGIVING!
• Expect minimum lanes closures throughout the project area during working hours.

Week of 11/13/17 (work hours 7:00am – 3:30pm)

Monday thru Friday
The contractor will continue with installing decorative crosswalks in the intersection of Route 31 and Route 275, Monument Hill Rd, and the parking lot of Coventry Corners.
The contractor will be installing the stamped concrete throughout the project area.
The contractor will be cleaning catch basins throughout the project area.
Expect minimum lanes closures throughout the project area during working hours.

Week of 10/23/17 (work hours 6:30am – 3:30pm)

Monday thru Friday
• Stamped concrete between sidewalk and granite curb from Bidwell Spirit Shoppe to Rte. 275
• Preparing parking lots /driveways at 1284 & 1276 Main St., Teleflex Building, and old firehouse building for asphalt paving. Paving is scheduled for Monday Oct. 30th.
• Landscaping throughout project may start on Thursday.
• Minimal lane closures this week.

Week of 10/16/17 (work hours 6:30am – 3:30pm)

Monday thru Friday

  • Placing topsoil throughout the project area.
  • Installing decorative light poles and pulling cable on the SB side of Main Street
  • Placing concrete for the remainder of the sidewalk
  • Reconstructing the parking lot between “Meet Me On Main” and the Teleflex Building
  • Minimal lane closures this week

Week of 10/09/17 (work hours 7:00am – 3:30pm)

Monday thru Friday

The contractor will continue with installing concrete sidewalks through the rock cut area and near 1265 Main St where the precast channel walls are.

The contractor will be working on installing the cover for the existing culvert at 1265 Main St and installing the remaining electrical/communication conduits in this area.

The contractor will begin installing topsoil in various locations throughout the project area.

Expect alternating traffic throughout the project area during working hours.

Week of 10/02/17 (work hours 7:00am – 3:30pm)

Monday thru Friday

PAVING THAT WAS NOT COMPLETED LAST WEEK IS SCHEDULED TO RESUME MONDAY OCTOBER 2nd. THE CONTRACTOR WILL BEGIN ON THE MILLED SURFACE AT THE INTERSECTION OF RTE 31 AND RTE 275. THIS WORK IS WEATHER DEPENDENT.

EXPECT HEAVY DELAYS DUE TO ALTERNATING TRAFFIC DUE TO PAVING, PLEASE FIND ALTERNATE ROUTES IF POSSIBLE.

The contractor will continue with concrete sidewalk through the rock cut area.

The contractor will continue with the water and sewer service for the Town Building at Shoddy Mills.

Week of 09/25/17 (work hours 6:30am – 5:30pm)

Monday thru Friday

Contractor will be raising all structures to final grade through the project area.

The precast channel in front #1265 Main St. and The Bidwell Tavern parking lot is scheduled to be stained on Tuesday September 26th.

PAVING IS SCHEDULED TO START ON WEDNESDAY SEPTEMBER 27th. THE CONTRACTOR WILL BEGIN ON THE GRAVEL SECTION OF THE NEW ROADWAY AND CONTINUE TO PAVE THROUGH FRIDAY. THIS WORK IS WEATHER DEPENDENT.

EXPECT HEAVY DELAYS DUE TO ALTERNATING TRAFFIC DUE TO PAVING, PLEASE FIND ALTERNATE ROUTES IF POSSIBLE.

MONUMENT HILL ROAD WILL CONTINUE TO BE CLOSED AT THE INTERSECTION OF MAIN ST. (RTE 31) NO THRU TRAFFIC. THIS ROADWAY IS EXPECTED TO BE OPENED BY FRIDAY SEPTEMBER 29th.

Week of 09/18/17 (work hours 6:30am – 4:30pm)

Monday thru Friday

Contractor will install new concrete driveway ramps at #1349 and #1340 Main St.

Contractor will finish installing the last pieces of Granite Curbing throughout the rock cut area.

Contractor will continue with underdrain, electrical conduit, and concrete sidewalks throughout the rock cut area on the southbound lane side.

Manhole structures will be raised to final grade throughout the project area.

THE SOUTHBOUND TRAFFIC LANE WILL BE GRAVEL UNTIL SEPTEMBER 27th.

PAVING SUBCONTRACTOR IS SCHEDULED FOR SEPTEMBER 27th. (WEATHER DEPENDENT)

MONUMENT HILL ROAD WILL CONTINUE TO BE CLOSED AT THE INTERSECTION OF MAIN ST. (RTE 31) NO THRU TRAFFIC

Minor delays to traffic for alternating traffic throughout the work period hours.

Week of 09/11/17 (work hours 7:00am – 3:30pm)

Monday thru Friday

Continuing the excavation of the rock cut to lower the new southbound lane to the northbound lane grade and installing granite curbing, underdrain, light bases and concrete sidewalks

THE SOUTHBOUND TRAFFIC LANE WILL BE MOVED INTO THE NEW AND FINAL LOCATION THRU THE ROCK CUT BY THE MIDDLE OF THE WEEK AND THE TRAVEL SURFACE WILL BE GRAVEL

MONUMENT HILL ROAD WILL BE CLOSED AT THE INTERSECTION OF MAIN ST. (RTE 31) NO THRU TRAFFIC

Minor delays to traffic for alternating traffic throughout the work period hours

Week of 09/04/17 (work hours 7:00am – 3:30pm)

Monday NO WORK HOLIDAY

Tuesday thru Friday

Continuing the excavation of the rock cut to lower the new southbound lane to the northbound lane grade and finishing the roadway drainage

Preparing the Precast Open Channel at #1265 Main St. for staining

Minor delays to traffic for alternating traffic throughout the work period hours