Author Archives: Shama McCormack

May 2018

Week of 04/30/18

• Install decorative fence on top of precast walls at open channel on both sides of Main Street.
• Seal the red stamped concrete between the sidewalk and curb.
• Repair driveway at 1284 Main Street & pave driveway apron at 1340 Main Street.
• No interference with traffic this week.

Week of 03/26/18

Contractor will be onsite on Monday March 26th

• Finish backfilling the precast retaining wall in front of Teleflex.
• Install concrete sidewalks, stairs, and clock tower in the new “Pocket Park” area in front of the precast retaining wall.
• Finish the installation of the precast retaining wall after the “Pocket Park” is in place.
• Complete miscellaneous punch list work throughout the project area.
• Very minimal impacts to traffic if at all, work to be done off the roadway.

Week of 03/05/18

Contractor will be back to finish the Project starting on Monday March 5th
• Finish backfilling the Precast Retaining Wall in front of Teleflex
• Install concrete sidewalks, stairs, and clock tower in the new “Pocket Park” area in front of the Precast Retaining Wall
• Finish the installation of the Precast Retaining Wall after the “Pocket Park” is in place
• Complete Miscellaneous Punch List work throughout the Project Area
• Very minimal impacts to traffic if at all, work to be done off the roadway

Month of March 2018
• Installation of the Timber Beam Rail at 1203 Main St is scheduled
• Metal Handrail/Protective Rail for the Precast Channel is currently being anodized at the shop, will be scheduled to be installed by the end of the month
• More information will be sent out when we have solid installation dates

Week of 12/25/17 and 1/1/17

No work for Christmas Day and New Year’s Day. The contractor will have light cleanup for the next couple of weeks. Utility work to move wires from the old poles to the new poles is tentatively scheduled depending on weather. Red Technologies will resume regular construction activities when the weather breaks. Little to no impacts on traffic.

Week of 12/11/17 (work hours 7:00am – 3:30pm)

Monday thru Friday
• Eversource is scheduled to be onsite moving overhead wires to the new poles.
• The Contractor will continue construction of the retaining wall at the Pocket Park (in front of Teleflex).

Monday & Tuesday
• Warning Lights will be on site installing street signs throughout project.

Tuesday Night (possible)
• Safety Markings will be on site line stripping the parking lots at Bidwell Tavern, Bidwell Spirit Shoppe, Rusty Relic and behind Italien Bistro/Phoenix Chinese.

Expect minimum lanes closures throughout the project area during working hours.

Week of 11/27/17 (work hours 7:00am – 3:30pm)

Monday thru Friday
• The contractor will be installing the stamped concrete and completing minor punch list work throughout the project area.
• Eversource is scheduled to be on site moving overhead wires to the new poles.
• The contractor will begin preparing the area for the retaining wall at the Pocket Park (in front of Teleflex).
• Expect minimum lanes closures throughout the project area during working hours.

Week of 11/20/17 (work hours 7:00am – 3:30pm)

Monday thru Wednesday
• The contractor will be installing the stamped concrete and completing minor punch list work throughout the project area.
• Eversource is scheduled to be onsite moving overhead wires to the new poles.
• NO WORK THURSDAY AND FRIDAY. HAPPY THANKSGIVING!
• Expect minimum lanes closures throughout the project area during working hours.

Week of 11/13/17 (work hours 7:00am – 3:30pm)

Monday thru Friday
The contractor will continue with installing decorative crosswalks in the intersection of Route 31 and Route 275, Monument Hill Rd, and the parking lot of Coventry Corners.
The contractor will be installing the stamped concrete throughout the project area.
The contractor will be cleaning catch basins throughout the project area.
Expect minimum lanes closures throughout the project area during working hours.

Week of 10/23/17 (work hours 6:30am – 3:30pm)

Monday thru Friday
• Stamped concrete between sidewalk and granite curb from Bidwell Spirit Shoppe to Rte. 275
• Preparing parking lots /driveways at 1284 & 1276 Main St., Teleflex Building, and old firehouse building for asphalt paving. Paving is scheduled for Monday Oct. 30th.
• Landscaping throughout project may start on Thursday.
• Minimal lane closures this week.